Assembly phase reveals Queen Elizabeth scale

Assembly of HMS Queen Elizabeth continues at pace in the dry dock at the Rosyth Dockyard, and as a result we are now starting to use new terminology.  Assembly of the centre section of the aircraft carrier is now  nearing completion  and  is known as Super Block 03, or SB03, in recognition that its constituent parts Lower Block 03, Centre Block 03 and various Sponson blocks are now assembled into a single, very large, entity.

Lifting of the final sponson block making up SB03 in January marked the end of dock cycle A and the Goliath crane is now parked for a fewmonths awaiting the start of dock cycle B, which will commence once the next shipment of major blocks to Rosyth is complete.

SB03 is a very significant structure. It is about 70 metres wide across the flight deck and overhangs the edges of the dry dock by a considerable amount on each side. It is nine decks high, with the flight deck being some 30 metres above the dock bottom, and is 65 metres long. As consolidation of the structure  progresses,  outfitting of the internal compartments and completion of pipe, cable and ventilation systems is  also moving ahead. When complete it will weigh in at about 14,000 tonnes. 

/g/w/r/TE_Blog_Carrier_Superblock.jpg

The first Superblock in dry dock, nice decks high and, on its own, the Navy’s biggest vessel

To put it in perspective SB03 on its own would be one of the largest ships in the Royal Navy!

At five decks above the base much of the width of the ship is taken up by the hangar,  with an opening on the starboard side where the forward aircraft lift will be installed. Above the hangar, the deck below the flight deck contains the weapon preparation areas. 

Many of these compartments are in a near finished state. Daily meetings of the production team now take place on board the ship in the Junior Rates dining hall and preparations are underway for starting to commission and set to work the electrical systems.

/y/b/e/TE_Blog_Carrier_Island.jpg

The Queen Elizabeth’s forward island structure under construction

The QEC has significant space given over to the storage, handling and deployment to the flight deck of air weapons. Traditionally these activities have involved a great deal of manual handling, using pallet trucks and other bespoke equipment and requiring a significant manpower.  The design aim for the Queen Elizabeth Class carriers is to achieve a sortie generation rate which is about six times faster than any previous Royal Navy aircraft carrier and to reduce the ship’s complement as far as possible.  Thus the design solution is a Highly Mechanised Weapon Handling System (HMWHS).  

This system will require about 50 people and can be operated by just 12, compared to some 160 which would have been needed to meet the sortie generation rate using conventional equipment.  The HMWHS comprises two complexes, each with deep stores using a  Bulk Stowage Pallet Handling System (PHS) . This PHS is in effect the heart of the design and is derived from commercial equipment.  Each pallet holds multiple containers of a particular weapon type and are shock mounted.  They are moved within the magazine and  into the appropriate weapon lifts by electrically powered vehicles operated by personnel from remote locations outside the magazines.  Two primary lifts service the weapon preparation areas and a further two weapon lifts serve the hangar. Pallets arriving at the weapon preparation areas are again moved by electrical vehicles to the preparation bays. Once weapons are prepared they are moved to the flight deck via two further dedicated Upper Stage Lifts.

Completion of the outfit of SB03 is generally working from the bottom up, thus while at the upper decks the final welding of the block buttsis taking place on the lower decks the bathrooms, showers and cabins are being finished off, compartment inspections carried out and doors locked.  The accommodation areas are being finished to a very high standard which I am sure the ship’s company will appreciate!

/y/c/o/TE_Blog_Carrier_cabin.jpg

Comfy: the cabons are being fitted out to a very high standard

There is also much progress with the second ship, HMS Prince of Wales. Members of the Aircraft Carrier Alliance and the UK MOD attended the Preliminary Design Review for the Aircraft Launch and Recovery equipment, electro-magnetic catapults and advanced arrestor gear, at General Atomics in San Diego at the beginning of February.  The proposed equipment for the UK is identical to that being supplied to the US carrier CVN 78 with just the minimum changes necessary to accommodate it in the UK ship, such as two catapults in lieu of four. 

Back in the UK at Appledore in Devon, the lower parts of the bow have been completed and will be shipped up to Rosyth in March. We will begin to see significant parts of HMS Prince of Wales around the dockyard in Rosyth. The steel cutting ceremony for Lower Block 02 of HMS Prince of Wales was held in Portsmouth on the 16th February –another significant milestone for the QEC project.


Readers' comments (19)

  • I love reading these updates, but I can't help thinking that the excitement over this considerable project is tainted somewhat by the fact that the carrier will be nigh-on useless for several years until we get aircraft to launch from it....

    It's a shame that scoring own goals and looking silly isn't a revenue-generating activity. If it were, then the UK would have its national deficit paid off in no time.

    Unsuitable or offensive? Report this comment

  • Let's buy some second hand aircraft to cover the gap. The US have square miles of out of date aircraft, some of which might even be our old sea Harriers, .....

    Unsuitable or offensive? Report this comment

  • Awesome in scale and scope - it makes you proud to be British and gives hope to the belief that we may rule the waves again some day.

    Unsuitable or offensive? Report this comment

  • If the QE flight deck is just 100 feet above the dock floor, what will the flight deck height be above the waterline and how will this compare to a Nimitz class aircraft carrrier?

    Could David confirm the planned barge transport dates the flight deck blocks being constructed at Camell Lairds.

    Unsuitable or offensive? Report this comment

  • No way Stuart...haven't you heard that HMS Victory is having a 5 year refit.

    Unsuitable or offensive? Report this comment

  • Its great that UK PLC can build this scale and complexity of vessel, but why do we need them? Surely the plan from around the mid 90's should hve been replacing the Invincible class through deck carriers with 25K ton versions (larger HMS Ocean's) with our own VTOL MRC aircraft. These new assets are too costly in every aspect and unriskable in a minor Falklands style conflict zone.

    Unsuitable or offensive? Report this comment

  • What happens when there is a power failure from a hit, how do the 50 cope with what was a 160 members job?

    Unsuitable or offensive? Report this comment

  • Seeing and reading the comments about the tight fit into the dry dock reminds me of naval histories I read of events before the first world war. GB invented the Dreadnought class battle ship, and the Grand Fleet had more of them than the German High Seas Fleet, but the Dreadnoughts' design was compromised by Britain's failure to create the correct dockyard resources for their building.

    Germany apparently started with the docks and then built the ships in them, making their assets better than their opposition. The difference in speed and manouevrability showed at Jutland.

    I do hope we haven't done it again.

    Unsuitable or offensive? Report this comment

  • Answering the questions raised on the 4th March comment. US aircraft Carriers are 11 decks high to the flight deck, so 2 decks more than the QEC, but the tween deck heights are lower.
    The first shipment of centre blocks from Camell Laird at Birkenhead will be on the 28th May, on the evening tide - weather permitting.

    Unsuitable or offensive? Report this comment

  • This is a massive undertaking that appears to be progressing well. It is just a shame that the rest of the British Navy is so depleted that once they are built and in service we really will not have sufficient other captial ships to defend them.

    The US for example has a number of fleets each with a carrier, various escorts and a submarine. We will have so few ships left that we will probably only be able to manage one escort!!

    Unsuitable or offensive? Report this comment

View results 10 per page | 20 per page

Have your say

Mandatory
Mandatory
Mandatory
Mandatory

Related images

My saved stories (Empty)

You have no saved stories

Save this article