Industrial safety and partitioning specialist Troax UK has designed and installed a multi-tiered, 10m-high environmental wall to optimise production conditions in the plating shop of Messier Services, a leading specialist in the repair and overhaul of landing gears and hydraulic units for military and regional aircraft

The project involved extending the existing three metre high partition which spans the length of the plating shop (around 50m in length) to the full height of the facility, which is around 10m.

Troax used modular solid steel panels from its Sabre range of single-skin partitioning to construct the environmental wall which has a dual function - segregating the plating shop from the surrounding area prevents fumes from escaping to adjacent engineering works and also reduces contamination to ensure optimum production conditions.

Messier Services has invested heavily in the Gloucester factory and the plating shop is part of a GBP 1.6 million metal finishing facility which is a European Centre of Excellence for single-aisle aircraft workshops.

Troax carried out a full design and installation service for the project through contractor Davroy Contracts.
A number of problems had to be solved during the course of the installation; because production equipment was already in place on the site and could not be moved, a 'cherry picker' was used to move overhead to reach the wall itself.

In addition, as the facility was fully operational throughout the installation.

Troax' staff worked over a holiday period and three further weekends to complete the project.

Commenting on the project, Ray Plenty of Davroy Contracts said: 'We've used Troax for around 30 years and as usual we're delighted with their first class products and excellent service'.

'This was potentially quite an awkward job - at 10m, the wall itself is very high and Messier's plating equipment had to remain in place meaning that installation was far from straight-forward but, as always, Troax' installation team was very efficient and extremely professional throughout, helping to devise a solution to these problems'.

'Messier are delighted with the result too'.

For more information on this company click here

To add your company click here


 


 

Have your say

Mandatory
Mandatory
Mandatory
Mandatory

My saved stories (Empty)

You have no saved stories

Save this article

Digital Edition

The Engineer May Digital Edition

Poll

Forward-looking flying car specialist Terrafugia has unveiled a new autopilot-equipped STOVL concept which it says could be on sale in 8-12 years. But will the science-fiction staple of the flying car ever take off?

Previous Poll

NASA chief Charles Bolden says that the agency is moving forwards with plans for a manned Mars mission, but there are significant ‘technology gaps’. Which of these is likely to be the most difficult to overcome?

Read and comment on the results here