Faster flow for Algeria’s pipeline

ABB has signed a $90 million contract with Algerian oil and gas company Sonatrach to expand and improve gas compressor facilities for the country’s pipeline system.

ABB has signed a $90 million contract with Algerian oil and gas company Sonatrach TRC to expand and improve gas compressor facilities for the country’s pipeline system. The improvements will speed up the flow of Algeria’s natural gas.

The order calls for ABB to design and construct a new gas compressor station at Tin Fouye Tabankort, 300 kilometres south of the refining hub of Hassi Messaoud. ABB will also upgrade an existing compressor station near the natural gas fields of Rhourde Nouss.

The new Tin Fouye Tabankort compressor station will be built along the existing GR1/GR2 gas pipeline to increase the overall transport capacity of the pipeline. Upgrading the existing compressor station at Rhourde Nouss will further increase the flow rate.

The current project is part of Sonatrach’s 30-month plan to install seven new turbo compressors rated at 25 MW each, and upgrade five compressors across Algeria’s Sahara region. ABB has several ongoing projects with Sonatrach, including the development of an oil treatment plant in the Bir Berkine basin, awarded in mid-2003.

Under the terms of the latest contract, ABB will be responsible for the engineering, procurement, construction, commissioning and start-up of the compressor units. The project is scheduled for completion by September 2006.