A study from Prognos and The Fichtner Group has found that that the cost of electricity from offshore wind can be reduced by around one third if it is developed consistently over the next decade.

‘The identified cost reduction potentials are based on the assumption that offshore wind power will be continuously developed and reach a capacity of nine Gigawatt or more by the year 2023. This is the way to gain project experience, to promote technological innovation and to significantly decrease costs,’ said Jens Eckhoff, president of Offshore-Windenergie in a statement. ‘Offshore wind power has a substantial cost reduction potential. However, the industry can only exploit this potential if there are reliable framework conditions to achieve significant market volumes.’

The study was commissioned by the German Offshore Wind Energy Foundation, Stiftung Offshore-Windenergie, along with associations and companies including DONG Energy Renewables, Iberdrola Renovables Offshore Deutschland Zwei, and Siemens.

It analysed the expected cost development of electricity generation from offshore wind power until the year 2023. For this purpose, two development scenarios were applied to evaluate three typical German sites for offshore wind farms.

The first scenario assumes a stable market development and describes the development of at least 9GW installed capacity in Germany by the year 2023.

In this scenario, the cost of offshore wind power decreases on average by about 31 per cent across all sites until 2023.

The second scenario assumes an optimum market environment with a development of 14GW until 2023. In this case, costs could decrease by up to 39 per cent.

‘The main driver for the cost reduction is a continuous technological development across the entire value-added chain. Particularly regarding investment costs, substantial savings can be achieved. Costs for support structures and other components as well as for the installation go down. Larger turbines reduce specific investment costs as the energy yield substantially increases,’ said Frank Peter of Swiss consultancy Prognos, co-author of the study.

The study also shows that due to increasing experience in project planning, plant construction and operation, the risks - and subsequently the financing costs - can be reduced.

In addition, improved logistics, such as the use of more powerful ships and an optimised infrastructure, can positively affect the costs of offshore plant operation and maintenance.

The analysis also shows that in an optimum market environment an expanded serial production and increasing competition will contribute to cost reduction.

‘In Germany, we have a number of projects ready and waiting,’ said Eckhoff. ‘Currently they lack the required investment security. In order to be able to use the experience gained from the first German offshore wind farms and to promote the further development of the industry, a timely implementation of these projects is necessary. This way offshore wind energy can make an essential contribution to tomorrow’s energy supply.’